The construction teams have been very busy on site since our last update two weeks ago, and it is wonderful to see so much progress each day.

 First Block:
  • All plaster and kitchens have been installed.
  • Garage doors have been installed on all the type 2 and 3 villas.
  • The type 1 villas have all been painted internally. Their courtyards will be concreted next week.

At this stage we are still aiming for the first villas to be available to move into in the last week of October.

Second Block:

  • The roof installation is nearly complete. The installation of external cladding is also underway.

At this stage we are still aiming for these villas to be completed and ready to move into in December, before Christmas.

Roads:

  • The road base and concrete kerb have been installed along the entrance road.
  • Stormwater is being installed on the high road above the first and second blocks in preparation for the road base to be laid.

Community Centre:

  • Internal rough-in of services is nearing completion
  • External cladding is being installed.

Please click on the links below to view the latest videos.